Project topic :
Installation of stay ring and spiral case equipment for the Karun Dam 4 turbines
Location :
Chaharmahal and Bakhtiari – Iran
Client :
Farab Company
Project highlights :
– Installation delivery to Voith Siemens Company according to current European standards with the lowest tolerance
– Work in the power plant pit with simultaneous 3 contracting teams in parallel in the vicinity and overhead
– Equipping the workshop twice before and after the flood
– Reconstruction and repair of parts damaged due to the flood
– Structure type: welded
– Weight: 750 tons
Year of implementation:
2006